Pant-y-Wal Extension
20 MW
Operational
This is the tab body content. It is typically best to keep this area short and to the point so it isn't too overwhelming.
Power: 20 MW
Operational Staus: Operational
Technical Details: The wind farm comprises 8 Nordex N90 2.5MW turbines, which are 80m to the hub and 125m to the tip. The site can produce up to 20MWe, which is the equivalent of the energy required to supply 15,000 homes. Nordex provide an operation and maintenance service and Pennant Walters provide site management and reporting services.
Partners: Construction: Turbine Supply Contract – Nordex Civil Engineering Contract – Walters UK Electrical Engineering Contract – Powersystems Ltd Grid Connection – Western Power Distribution Walters UK assumed the role of principal contractor.